Project Title and Scope: 12 mile road at the Charlotte River. Design/Build replacement of obsolete metal culvert with 30’ span x 12’ rise pre-cast concrete box culvert conforming to MDOT HL 93 MOD (*1), 2017
Owner/Contractor: Chippewa County Road Commission, Sault Ste. Marie, Michigan
Engineers: U. P. Engineers and Architects and Salmons, P.C.(precast)
Precast Concrete Producer: Upper Peninsula Concrete Pipe Co. Inc.
Project Title and Scope: Delta County G17 over the Days River,56’ span x 4’ rise,conforming to HL 93. Replacement of structurally deficient bridge. 2018
Owner and Contractor: Delta County Road Commission, Escanaba, Michigan
Engineers: U.P. Engineers and Architects & Pretek Group (precast)
Precast Concrete Producer: Upper Peninsula Concrete Pipe Co., Inc
Project Title and Scope: Delta CountyI-26over the Tacoosh River,36’ span x 4’ rise conforming to HL 93MOD. Replacement of structurally deficient bridge. 2017
Owner and Contractor: Delta County Road Commission, Escanaba, MichiganEngineers: U.P.
Engineers and ArchitectsNote: precast wing walls and load bearing headwalls
Precast Concrete Producer: Upper Peninsula Concrete Pipe Co., Inc.
Copyright © 2022 LowSpan. All Rights Reserved.